January 1 - March 31, 2013
- Executed overlash agreement with Russell Muni. Cable TV & Internet.
- Executed pole attachment agreement with Time Warner Cable Northeast, LLC.
- Executed Indefeasible Rights of Use agreement with Chicopee Elec. Light Dept.
- Executed Indefeasible Rights of Use agreement with Holyoke Gas & Elec. Dept.
- Executed permitting agreement with Pan Am Railways.
- Executed permitting agreement with New England Central Railroad.
- Received 3,002 Verizon pole licenses for a total of 31,603 (96%).
- Received 3,218 electric utility pole licenses for a total of 29,428 (97%).
- Released 155 fully-licensed fiber miles to construction for aerial installation for a total of 895 miles for the project (96%).
- Installed 305 miles of messenger strand for a total of 775 miles for the project (83%).
- Installed 388 miles of aerial fiber optic cable for a total of 676 miles for the project (72%).
- Received licenses for 14 miles conduit for a total of 39 miles to date (93% complete).
- Installed 8,131 feet of conduit for a total of 15,312 feet for the project (32%).
- Completed designs for 8 Community Anchor Institutions for a total of 790 locations (97%).
- Completed 44 Community Anchor Institution site installations for a total of 582 locations for the project (72%).
- Completed 81 Community Anchor Institution fiber terminations for a total of 260 locations for the project (32% of locations complete).
- Completed 6 Point of Interconnection and collocation site installations for a total of 17 to date (63%).
- Completed turnover of first network segment to Network Operator, connecting 3 Points of Interconnection and 2 regeneration sites.
- Executed 4 Letters of Intent with an Internet Service Providers for a total of 31, as well as signing 5 connecting agreements to total 13 connecting agreements for the project.
- Submitted 4th formal Award Action Request for modifications of construction plans pending NTIA approval of route adjustments.