October 1 - December 31, 2013
- Received 125 additional Verizon pole licenses for a total of 32,638 (99% complete).
- Received 128 additional electric utility pole licenses for a total of 30,330 (99% complete).
- Installed 3 additional route miles of messenger strand for a total of 883 route miles for the project (99% complete).
- Installed 8 additional cable miles of aerial fiber optic cable for a total of 998 cable miles (including slack and sag) for the project (99% complete).
- Installed 792 additional feet of conduit for a total of 48,365 feet for the project (100% complete).
- Completed 15 additional Community Anchor Institution site installations for a total of 782 locations for the project (99% complete).
- Completed 239 additional Community Anchor Institution fiber terminations and testing for a total of 537 locations for the project (98% of locations complete).
- Completed turnover of 12 additional Points of Interconnection to Network Operator (70% complete).
- Completed acceptance testing on a total of 24 network segments (67% complete).
- Completed acceptance testing on a total of 726 Community Anchor institutions (92% complete).